FOOD-SUP-3.2.2

Prerequisite Programmes, Supplier Approval and Reviewing the Plan

Explains why HACCP collapses without prerequisite programmes, details each programme and its typical yacht failure mode, covers supplier approval and traceability, and sets out the triggers for reviewing the HACCP plan.

Your HACCP plan is excellent. Every CCP is monitored, every limit justified, every record signed. And your guests still get ill — because a cockroach in the dry store, a cracked worktop and a stew who never had a hygiene induction are not CCPs, and your plan quietly assumed all of that was already handled. That assumption is what prerequisite programmes are.

Why HACCP fails without prerequisites

HACCP controls the significant hazards at defined points. It is built on the assumption that a basic hygienic environment already exists. If the foundation is not there, the plan floats on nothing: you cannot HACCP your way out of a filthy galley, a broken fridge or an untrained crew.

The prerequisite programmes

Programme What it must specify Yacht failure mode
Cleaning and disinfection Schedule: what, with which chemical, at what dilution, contact time, how often, by whom, signed "Deep clean" with no contact time; sanitiser wiped straight off; ice machine never descaled
Pest control Proofing, monitoring, contractor, evidence log, no harbourage Cardboard provisions boxes brought straight into the dry store — the classic cockroach import
Maintenance Planned maintenance of fridges, chillers, seals, surfaces, probes Failed door seal on the walk-in nobody reported; chipped worktop harbouring bacteria
Personal hygiene Handwashing, clothing, jewellery, cuts covered, no bare-hand contact with RTE food Handwash sink used as a prep sink; gel instead of soap and water
Supplier approval Approved list, specification, checks, traceability, delivery standards Provisioning agent chosen on price and speed in an unknown port
Waste management Segregation, covered bins, removal frequency, ashore disposal (and MARPOL) Uncovered galley bin during service in the heat
Training Who needs what, refreshers, records Seasonal stew handed a knife and a section on day one
Water and ice Potable bunkering, dedicated hose, tank cleaning, chlorine residual, ice machine hygiene Bunkering from a hose that has been lying on the quay

Supplier and provisioning approval

You cannot audit a supplier in every port, but you can build a defensible approach:

  • Keep an approved supplier list with a named contact and a written specification.
  • Where possible, ask for evidence: HACCP certification, temperature-controlled vehicles, traceability.
  • In unknown ports, weight the control toward acceptance: probe, inspect, reject, and record. What you can prove at the gangway is the control you actually have.
  • Maintain traceability — you must be able to trace what you served back to a delivery. Keep delivery notes and, for high-risk items, retain the label.

Reviewing the plan

The HACCP plan is a living document. Review it — and record the review — whenever:

  • The menu changes, or a new technique appears (sous vide, sushi, fermenting, curing).
  • The crew changes — a new chef brings new methods and different competence.
  • The itinerary changes — a Caribbean season, a remote cruising ground, a transatlantic passage.
  • An incident, complaint or near-miss occurs.
  • On a fixed schedule regardless — at least annually.

Onboard Notes

  • Contact time is the most commonly ignored word in cleaning. Write it on the schedule and check it.
  • The day the new chef joins is the day the HACCP plan needs reading — by both of you, together.

Scope note: xplor is not an approved centre or an accredited training provider. This lesson is preparatory study only - no certificate and no regulated qualification is awarded here, and a Level 3 supervising food safety award must be sat and assessed with an approved centre of a regulated awarding organisation.

Practice questions

5 questions
recallcore

recall · core

What are prerequisite programmes, and why does HACCP fail without them?

recallcore

recall · core

How do you approve a supplier when you are provisioning in a remote port and cannot audit them?

recallcore

recall · core

What events should trigger a review of the HACCP plan?

scenariostretch

scenario · stretch

The yacht is about to leave the Med for a three-week Atlantic crossing followed by a remote Caribbean itinerary, with a new chef joining and a guest who has declared a severe peanut allergy. What does your HACCP review cover?

oralstretch

oral · stretch

Give a typical yacht failure mode for three different prerequisite programmes.

Independent study. xplor is not an Ofqual-regulated awarding organisation or an approved centre, and awards no qualification. Useful preparation if you are working toward a Level 3 supervising food safety award, which must be sat with an approved centre.