AUS-M3000-Y-L2.1

Ocean passage planning and weather routeing

A passage plan runs **berth to berth** — from the moment the last line comes off to the moment the first line goes on at the other end, pilotage included. Not sea buoy to sea buoy. The groundings happen in the bits people leave out.

Entry & progression

This certificate is any operating area. That phrase is only worth anything if you can plan an ocean crossing properly. The plan is the master's document. You may delegate the drafting; you never delegate the responsibility.

The four stages

A frontal depression

  1. Appraisal. Gather everything before you decide anything. Charts and publications for the whole route, corrected. Routeing guides, ocean passage publications, pilot charts and climatic data for the season. Load line zones. Traffic separation schemes. Piracy and security areas. Emission control and discharge areas. Draft, air draft, under-keel clearance. Fuel range with a real reserve, not an optimistic one. The vessel's own limits: sea state, motion, the SMS.
  2. Planning. Lay the tracks. Great circle where the saving justifies it, rhumb line where it does not, composite great circle where a limiting latitude bites. Waypoints that make sense to a tired watchkeeper at 0300. No-go areas marked. Abort points and contingency anchorages named — not assumed.
  3. Execution. Adjust for what the appraisal could not know: the actual forecast, the actual ETA, the actual guest movements, the actual fuel burn.
  4. Monitoring. Fix, cross-check, parallel index, watch the set. Every position from one source is a rumour.

Weather routeing

A yacht is not a bulk carrier and the objective is not always least time. Least time may be the worst possible track for a vessel with twelve people aboard who paid a great deal of money not to be thrown across a saloon.

  • Shore-based routeing services give you a recommended track and daily updates. They do not command your vessel. Their advice is an input, not an order — and the liability for taking it stays with you.
  • On-board routeing using GRIB data and your own performance curves gives you control and immediacy. It is only as good as your discipline in updating it.
  • Motion, not just wind. Swell period against your natural roll period is what makes guests ill and crockery fly. A 25-knot beam sea with a long swell can be far more punishing than 35 knots on the bow.
  • Tropical systems. Plan to be nowhere near them. Give sea room early, when it costs you a day. Later, it costs you the vessel.

The pressure that actually kills yachts

Almost nothing in commercial shipping compresses a master like a charter schedule. The guests fly into Palma on Saturday. The owner is expecting the vessel in Antigua for Christmas. Everyone aboard knows what the calendar says, and the calendar does not know what the barometer says.

WARNING — The plan is not a contract A passage plan is a considered intention, prepared in a warm office with good coffee, using the best information available at the time. When the information changes, the plan changes. A master who follows a plan into weather because the plan said so has confused a tool with a duty. Deviate. Log why. Tell the office afterwards, not before.

Fuel is a planning input, not an afterthought

Yachts are thirsty and their range figures are usually quoted at economical speed in flat water. Plan the passage at a speed you can actually hold, add a margin for heavy weather consumption, add a diversion, and then decide whether you can make the crossing. Bunkering options mid-ocean are, famously, limited.

And check the tanks against the plan, not against the gauges. Slack tanks are also a stability problem — Lesson 4.1.

Practice questions

5 questions
recallcore

recall · core

A passage plan is prepared: (a) Berth to berth, including pilotage waters at both ends (b) Sea buoy to sea buoy (c) From the pilot station outbound to the pilot station inbound (d) For the ocean legs only; coastal legs are the OOW's responsibility

recallcore

recall · core

The four stages of passage planning are: (a) Appraisal, planning, execution, monitoring (b) Research, drafting, approval, filing (c) Charting, plotting, sailing, arriving (d) Assessment, approval, departure, arrival

recallcore

recall · core

A shore-based weather routeing service issues a recommended track. The master: (a) Must follow it - it is a professional recommendation (b) Must follow it if the company has paid for the service (c) Must follow it unless the owner objects (d) Treats it as an input; the decision and the liability remain the master's

recallcore

recall · core

For a yacht carrying guests, the optimum weather route is: (a) Always the least-time track (b) Always the great circle (c) Whatever the routeing service recommends (d) Often not the least-time track - vessel motion and comfort are legitimate planning inputs

recallcore

recall · core

When the forecast changes and the plan no longer suits the conditions, the master should: (a) Deviate as required, log the reason, and inform the office afterwards (b) Follow the plan - it was approved before departure (c) Seek the office's approval before deviating (d) Seek the charterer's approval before deviating