Chartwork, position fixing and passage planning

Chartwork is the core practical skill tested in the Navigation paper and the daily craft of the watch. The OOW must know the charts and their projections, command the several ways of fixing and estimating position, and tie them together in a disciplined four-stage passage plan.

Charts, projections and symbols

Navigators work mainly on the Mercator projection, on which meridians are parallel and a straight line is a rhumb line of constant course — ideal for plotting, at the cost of scale distortion that grows toward the poles. Distance is therefore always measured on the latitude scale beside the vessel's position, never the longitude scale. The gnomonic projection, on which a great circle plots as a straight line, is used for ocean great-circle planning and for harbour plans. Every symbol and abbreviation is defined in Admiralty publication NP5011, and the chart's horizontal datum must be checked because a GNSS position on WGS84 may need shifting to match an older chart datum.

Fixing and estimating position

Type Meaning Reliability
DR (dead reckoning) Position from course steered and distance run only Lowest
EP (estimated position) DR corrected for tidal set/rate and leeway Better
Fix Two or more position lines that cross Good
Running fix One position line transferred along the ground track to cross a later one Good when only one object is available
The position types, in ascending order of confidence.

Position lines come from compass bearings, radar range and bearing, horizontal or vertical sextant angles, a line of soundings, or the rising or dipping distance of a light. Three position lines crossing in a small triangle — a tight 'cocked hat' — give confidence; a large cocked hat signals an error to resolve, not a position to accept, and the OOW should treat the vessel as being at the corner nearest any danger.

The four-stage passage plan

Appraisal, Planning, Execution, Monitoring

  1. Appraisal — gather every source: charts, sailing directions, light lists, tide tables and stream atlas, routeing charts, navigational warnings and the ALRS, and assess the risks of the whole passage.
  2. Planning — lay off the intended track berth to berth, marking no-go areas, clearing bearings, wheel-over points, contingency anchorages, abort points and the required underkeel clearance.
  3. Execution — brief the bridge team, confirm the plan against the actual tide and weather, and adjust timings for tidal gates before getting underway.
  4. Monitoring — fix and cross-check position by primary and secondary means throughout, and act early the moment the vessel is set off the plan.

WARNING — Never trust a single source A confident but wrong GNSS position has grounded many ships. Cross-check the electronic position against visual bearings, radar ranges and the echo sounder, and keep a running EP so a jump in position is obvious.

Practice questions

5 questions
recallcore

recall · core

On a nautical chart, distance is measured using the: (a) Longitude scale along the top and bottom (b) Latitude scale at the sides, level with the vessel (c) Compass rose (d) Depth contours

recallcore

recall · core

An estimated position (EP) improves on a DR because it also allows for: (a) Compass error only (b) Tidal set/rate and leeway (c) Chart datum (d) Variation only

recallcore

recall · core

A large 'cocked hat' from three bearings tells the OOW that: (a) The fix is excellent (b) There is an error to resolve; assume the position nearest danger (c) Variation is zero (d) The gyro has failed

recallcore

recall · core

The first stage of a passage plan, gathering all information, is: (a) Execution (b) Appraisal (c) Monitoring (d) Planning

recallcore

recall · core

A great-circle route plots as a straight line on which projection? (a) Mercator (b) Gnomonic (c) Transverse Mercator only (d) None